I.PARK1’s target of beginning full operation this year is expected to be postponed after an October fire damaged equipment in its third incineration module. The Environment and Ecology Bureau said the facility’s actual start-up timing would be decided once a repair plan had been settled.

The fire on October 26 prompted the evacuation of 970 people. One person who felt unwell was taken to hospital. The blaze affected roof aluminium panels, steel components supporting the roof and parts of the ventilation system, including ducts and pipes.

The contractor and a registered structural engineer are assessing the roof and testing the affected incineration and flue-gas treatment systems, electrical and mechanical systems, and fire-services systems and equipment. The assessments will inform the repairs.

I.PARK1 temporarily stopped receiving waste after the fire. Following a comprehensive inspection, its first and second modules began gradually resuming operations on October 30.

The bureau said the fire investigation ruled out an electrical fault, deliberate arson and chemicals spontaneously catching fire. Welding work or smoking remained possible causes.

Under the contract, the contractor is responsible for repairing damage that occurs before the facility formally begins operation, the bureau said. The contractor has also bought contractor’s all-risks insurance under government works requirements.